School Building Project

The Governors have a strategic plan for improving our school environment.  This is split into phases:


Phase 1 & 2 - Completed in August 2009 at a cost of £575,000. 

New Reception and Year 1 Classes, cloakrooms and toilets (see photo of the new outdoor areas in Reception and Year 1 below)

  • Year 5 Classroom
  • Music Room
  • Group Room
  • New Staff Room

Phase 1 & 2 Photos


Phase 3a - Completed in January 2012 at a cost of approx. £400,000

  • New school entrance
  • Key Stage 2 toilets
  • Library
  • New offices
  • External courtyard area

Download a copy of the plans

Phase 3a Photos


Phase 3b - Completed September 27th 2013 at a final cost of £106,000

  • Rebuild Year 3 and Year 4 cloakrooms
  • Enlarge Year 3 and Year 4 classrooms

Phase 3b Photos


Phase 4 COMPLETED OCTOBER 2017 AT A COST OF £95,000

  • Remove Year 2 toilets and storage rooms to provide an extension to Year 2 classroom

If you haven't already done so, please join the School's Voluntary Contribution Scheme to help us achieve our plans, £2.50 per family per month really makes a difference. Find out more.